High-speed rail cost could soar


Download story podcast

10:00 PM PDT on Saturday, August 27, 2011

BY TIM SHEEHAN
THE FRESNO BEE
For two years, the California High-Speed Rail Authority said it could build 520 miles of high-speed train tracks between San Francisco and Los Angeles for about $43 billion.

But that figure -- long derided as unrealistic by critics -- went off the rails this month when the authority released detailed environmental reports for its proposed Merced-Fresno and Fresno-Bakers- field sections, the first two segments the agency wants to start building next year.

The authority's most optimistic estimates for the San Joaquin Valley sections alone total about $10 billion; route choices could run the price to $13.9 billion.


AP
This image provided by the California High-Speed Rail Authority shows an artist's conception of a high-speed rail station in California. The rail authority wants to begin work next year.
That's a far cry from the 2009 estimate of $8.1 billion.

If projected costs can rise by as much as 71 percent in the San Joaquin Valley -- a relatively flat, straightforward stretch -- what will happen when tracks must be built through mountains and across cities in the Bay Area or Southern California?

If costs escalate statewide as much as in the San Joaquin Valley, the price to build the system from San Francisco to Anaheim could leap from the 2009 estimate of $43 billion to as much as $67.3 billion, even before buying any trains.

Eventually the statewide line will run from San Diego to Sacramento. Bullet trains are planned to run through the Inland area, traveling to Ontario International Airport and then either eastward to San Bernardino and Riverside before going south to Murrieta, or southbound through Corona to Murrieta. Any Inland line would offer quick connections to downtown Los Angeles and San Diego.

Some critics are saying, "I told you so," and others worry about even more cost increases in the San Joaquin Valley and statewide before a decade of construction begins in late 2012, as planned.

"It is about time that more realistic numbers are being used," said Elizabeth Alexis, co-founder of Californians Advocating Responsible Rail Design, a group that has long doubted the authority's estimates.

Roelof van Ark, the rail authority's CEO, acknowledged last week that the earlier estimates, set forth in a 2009 business plan to the Legislature, were "a little bit optimistic."

Construction plans have changed in the San Joaquin Valley between 2009 and now, van Ark said.

He said an updated plan due before the Legislature in October will reflect the higher costs for the valley -- and statewide.

"What you're seeing in the Central Valley, you are going to see in the other parts of the state as well," van Ark said. "Quite a few of the components (that add to the cost in the valley) will definitely carry into other parts of the state. However, some of them could be even larger."

'WE KNOW MORE NOW'

The higher estimates in the draft environmental impact reports for the San Joaquin Valley segments are the result of engineers refining the route options and gaining a better understanding of construction challenges, van Ark said.

"We know more now," said van Ark, who was hired by the authority months after the 2009 plan was prepared. "When you start designing systems like this, you look at the alignment, the cities, the rural areas, and you make assumptions. ... (But) you don't have the detail to consider what real costs are going to come about."

With that detail in hand, the authority has identified about $5.8 billion in new costs, including:

About $3 billion more to build about 36 miles of elevated tracks over the cities of Madera, Chowchilla and Corcoran to avoid closing streets.

About $844 million more for elevated structures, tunnels, bridges, overpasses and undercrossings to cross waterways, streets, highways and railroads along the route.

About $685 million more for earthworks and retaining walls to raise the tracks above flood plains.

Van Ark said that since the first estimate, prices also have gone up for materials, such as steel, needed to build the system.

Between Merced and Fresno, the cheapest route option -- now estimated at about $3.8 billion -- follows the Union Pacific freight railroad and Highway 99 between Merced and Chowchilla. It loops west around Chowchilla, then heads east to follow the BNSF Railway track around Madera to the east.

The line then crosses the countryside to return to the UP tracks and Highway 99 by the time it reaches the San Joaquin River, and remains along the UP tracks through downtown Fresno.


The most expensive option is one that follows the UP tracks and Highway 99 all the way from downtown Merced through Chowchilla and Madera to downtown Fresno. At an estimated cost of $6.7 billion, it includes the stretch of elevated tracks from north of Chowchilla to south of Madera.

Between Fresno and Bakersfield, the route roughly follows the BNSF Railway tracks, except for a stretch that crosses the Kings County countryside east of Hanford.

The most expensive variation, at about $7.2 billion, would pass through the cities of Corcoran, Wasco and Shafter and the historic community of Allensworth, with elevated tracks through Corcoran.

The lowest estimated price, about $6.2 billion, is for a route with bypasses around those towns.

The new cost projections in the valley are about in line with what Alexis' Californians Advocating Responsible Rail Design group predicted, based on figures in the authority's application for federal stimulus funds this year.

"We had already built in the escalation to our cost figures, so our current estimate is consistent with newly released information," Alexis said. "The budget numbers in the federal applications revealed the much higher price tag to those of us keeping close tabs on the project."

"Hopefully," she added, "all the cost surprises on this (valley) segment going forward are good ones."

'SALES, MARKETING'

Research shows that for decades, cost overruns are the rule rather than the exception for big transportation projects in general, and for big rail projects in particular. And California's proposed high-speed train system is a biggie.

"Even in the best of times, large infrastructure investments have a dismal performance record in terms of cost overruns, delays, and benefit shortfalls," Oxford University program-management professor Bent Flyvbjerg wrote in a 2009 research article in the Oxford Review of Economic Policy.

In 2009, the cost for San Francisco-to-Anaheim was estimated at about $39.3 billion, or just under $43 billion by the time trains were purchased to run on the system.

Lynn Schenk, a former congresswoman from San Diego and a member of the rail authority's board, said the 2009 plan was created in "an atmosphere of wishes, hopes and faith, and ... was more of a sales and marketing piece" than a reliable prediction of costs.

Schenk said the October business plan will be "just about our last chance to rebuild confidence in this project, and us, that we can get this done" in the face of growing statewide concern over the rail project.

Van Ark also understands the implications of the new business plan, which will detail not only the costs for the statewide system, but also how the authority expects to pay for it.

And, he added, it will paint a much more realistic picture than the 2009 plan.

"We -- I say we even though I wasn't around -- we were a little bit optimistic in those days," van Ark said.

The authority's new estimates are priced to include all types of route options, "and these have all been cross-checked by a second group of costing engineers," he added. "I want to make sure I'm right when I go out and talk about these things."

California has about $6.3 billion available to start construction, a combination of federal stimulus funds and money from Prop. 1A, a $9 billion bond measure approved by California voters in 2008. Planners decided the best place to use that first chunk of money is the San Joaquin Valley.

"We will build as many miles as we can out of that $6 billion," van Ark said.

The Associated Press contributed to this report.